Case Studies

A Refreshingly Cool Install

A leading soft drink manufacturer was investing significantly in new air conditioning as part of their decarbonisation objective at their Lutterworth site. C&B were commissioned with the task comprising of Design, Supply & Installation of 7 new three-phase supplies across 2 external compounds providing power to the condenser units.

Each Supply had a challenging route through the warehouse & above ceilings before dropping into a duct system externally. We installed new tray work along our cable routes before pulling in over 450m of SWA cabling.

Objectives:

  • Install new tray work through a busy warehouse & office area, causing as little disruption to staff as possible.

  • Design & Install new three-phase supplies to air-conditioning units from existing mechanical distribution panels    

  • Provide clear & concise labelling to ease future maintenance.

CONTACT US

For any questions, queries or a free quote on any of the services we provide, please contact:

01908 579461

Call Us

E-Mail Us

info@candb-electrical.co.uk

Visit Us

311 Hayley Court,
Foxhunter Drive, MK14 6GD

©C&B Electrical Contractors LtdTM 2024.